KpH were awarded the project of removing 1no. Sludge Thickener and associated pipework.

The project was within a live sewage treatment plant with vehicle movements through the day so works and waste removal had to be carefully coordinated.

Scope of Works

  • KpH carefully planned out a safe method of removal for the plant, taking into careful consideration the busy working site
  • A vacuum tanker was set up at the closest point possible for the team to decontaminate and clean the sewage drum thickener and associated pipework
  • Operatives then unbolted the drum thickener from the slab and disconnected associated parts to leave it free standing ready for the Hiab lift