Projects
-
Buffer Vessel Removal
Brief Description:
We were awarded the project by longstanding client, Omega Building Services to remove 1no. 3,000ltr buffer vessel.
The vessel was located in a live boiler room and within close proximity to tenants, therefore great care needed to be taken to protect the live services and reduce any disruption.
-
Below Ground Tank Removal, Tonbridge
Brief Description:
KpH Environmental were awarded the project to clean, degas and remove 1no. 1500g belowground water filled petrol tank for new client S. Smith & Sons Builders Limited.
S Smith & Sons (Builders) is a well established, family run business located within a residential area. KpH carefully planned out the safe method for the cutting and removal of the tank taking into consideration the small working area and the tank being close to live services including overhead cables and site drainage.
-
Creosote Tank Clean & Removal, Reading
Brief Description:
We were awarded the contract by new client Stonewood Builders to remove an underground tank and creosote contamination.
The site is located at a Country Estate Yard, located to the south west of Reading in Berkshire where commercial and light industrial activities are undertaken including a gunsmith, offices, a tractor shed, a vehicle workshop and various buildings used for storage.
-
Underground Tank Decommissioning & Interceptor Cleaning
Brief Description:
We were recently awarded the contract to decommission 6no. Tanks—2no. 15,4000ltrs,3no. 8810ltrs and 1no. 6610ltrs by new client Adkins Consultants.
The site was on a busy road within a built up area so the team had to be considerate with noisy works and vehicles in and out of site.